Follow Datanami:
May 8, 2015

How Hadoop Solved BT’s Data Velocity Problem

Like most large corporations with millions of customers, BT (British Telecom) has an extensive collection of databases, and is constantly moving data in and out of them. But when data growth maxed out a critical ETL server, it found a solution in a distributed Hadoop system.

With £18 billion (about $30 billion) in revenue last year, BT is one of the largest telecommunications provider in the world, and serves more than 18 million consumers and nearly 3 million businesses in the UK. Its £12.5-billion acquisition of the mobile phone network EE Limited will expand its reach even further.

Several years back, BT ran into a little snag with its data transformation processes for its business customers (the consumer data is managed separately). Data about new UK businesses would flow in from Dun & Bradstreet, and BT would dole it out to the requisite line-of-business systems accordingly.

“Being an old company, we’ve managed to spread our customer data over 12 different significant customer databases,” BT’s chief data architect Phillip Radley said during this week’s Strata + Hadoop World conference in London. “So every night we had a massive ETL job, a billion records that have to be compared and contrasted, to reconcile the updates and make sure that all of the systems are up to date.”

BT chief data architect Phillip Radley

BT chief data architect Phillip Radley

The batch system worked well enough, but eventually the batch window maxed out. In other words, it took 24 hours to process 24 hour’s worth of data, Radley said. Since the process was running on an old ETL software package on an old server in an old data center that BT wanted to close, it started looking to phase out the old stuff with newer replacements.

Initially, BT considered adding a new relational system to take over the ETL work. Then Radley had another idea. “I sat down with some colleagues, and they said, ‘You know what, that thing would work on Hadoop. It’s basically a data velocity problem. We need to process that data faster and increase the volume,'” he said.

BT contracted with Cloudera to put a production Hadoop cluster together, and replace the batch ETL application with Java-based MapReduce routines. “We went from PowerPoint to production in nine months–pretty good by our standards,” Radley said. “And the net result is we now achieved a velocity increase of a factor of 15. So the data cycle now takes eight hours and we process five times the amount of data.”

What’s more, BT implemented its 50-node CDH cluster in its Sheffield data center without hiring a bunch of “Hadoopy” experts, Radley said. “We took some of the world’s best Linux admins and upskilled them to run Hadoop,” he added. “They thought that was great. They got new skills. They’re very happy with that.”

BT_4It all seemed well and good, but BT’s CFO was a skeptic who wouldn’t be won over easily. “Our CFO said ‘Big data is big hype. We don’t believe you. Don’t keep coming back in here unless you deliver a return on investment,'” Radley said. So after tabulating costs and benefits, Radley figures his one-year return on investment is in the 200 percent to 250 percent range.

Hadoop may carry a bit of hype, but if it can deliver the goods at the end of the day, who cares? “The business sponsor doesn’t know it runs on Hadoop, and frankly they don’t care,” Radley says. “All they know is now they’re working with today’s data rather than yesterday’s data. And also we’re saving them a lot of money. Putting it on Hadoop was much cheaper than doing it with a [standard] system.”

As the saying goes, no good deed goes unpunished, and soon BT was calling upon its Hadoop cluster to do new things. The first of those is tracing network connections in support of BT’s efforts to sell fast Internet connections (from 40 Mbps to 300+ Mbps). As Radley explained, determining whether a given customer in a given part of the UK has the copper wiring necessary to support the delivery of super-fast Internet is no simple task.

“Whether you can get that service is very dependent on how long the copper is, how good the copper is, how many joints there are in the copper, and it means we have a lot of very detailed network analyses,” Radley said. “You can imagine 24 million homes, individual wire segments connecting each of them together. That’s a lot of data to compare and contrast. You have to get all the inventory and all the performance and test data, and join that up and figure it out.”

The company–which is working with Hive and has some Spark stuff going too–has similar plans to use Hadoop in support of maintaining quality of service (QOS) for its TV service. What’s more, it’s also counting on Hadoop to assist in the roll-out of its “4G In the Home” initiative, in which BT will essentially place shrunken cell towers directly in customers’ homes.

“That means, instead of managing 70,000 to 80,000 base stations around the UK, we have to manage 5 million tiny base stations, one in every home. That’s an awful lot of telemetry data,” Radley said. “Previously it wouldn’t have been cost effective for us to do that efficiently. But with something like Hadoop, we can [handle] all that telemetry, hundreds of measures every 10 minutes from millions of devices.”

Related Items:

Wanted: A Plug-In Architecture for Hadoop Development

Why Big Data Isn’t Changing Everything (At Least Not Yet)

Does Hadoop Need a Reality Check?

 

 